Penns Valley Rails-To-Trails Program
Penns Valley Rails-To-Trails Map
The Gregg Township Supervisors, in collaboration with the Centre County Planning and Community Development Office, have decided to pursue the development of a Rails-to-Trails Feasibility Study throughout a majority of the Penns Valley Region and a section of the Centre Region along the former historic Lewisburg-Tyrone, Centre and Spruce Creek railroad alignments.

This new trail system is envisioned as one of the hallmark projects developing from the Centre County Recreation and Greenways Plan and would serve as a natural link between the easternmost sections of the Centre Region, in particular Harris and College Townships and their respective communities of Boalsburg and Lemont, and the Penns Valley connecting core communities such as Centre Hall, Spring Mills, and Coburn while also providing linkages to key community educational, recreational, historic and cultural resources.
PVRT on Facebook
Public Meetings
  • Public Meeting #1 - March 12, 2013

Minutes/Q&A
Presentation
Written Comments

  • Public Meeting #2 - November 19, 2013

Presentation

Study Committee Meetings
  • Steering Committee Meeting #4 - February 27, 2014
Agenda
Presentation
  • Steering Committee Meeting #3 - September 10, 2013
Agenda
Presentation
  • Steering Committee Meeting #2 - February 12, 2013

Minutes
Presentation

  • Steering Committee Meeting #1 - October 9, 2012
Minutes 
Presentation

Consultant Selection Schedule:

  • RFP Available: May 24, 2012
  • Optional Pre-Bid Meeting: June 1, 2012
  • Deadline to Submit Questions: June 8, 2012
  • Deadline for Response to Questions: June 15, 2012
  • Proposal Due Date: July 6, 2012
  • RFP Opening: July 12, 2012 - Gregg Township Board of Supervisors Meeting
  • Complete Evaluations: July 27, 2012
  • Interviews (If necessary): August 1, 2012
  • Selection by the Township: August 9, 2012 - Gregg Township Board of Supervisors Meeting
  • Notice of Selection: August 10, 2012
  • Negotiation of Contract: August 17, 2012
  • DCNR Review of Contract: August 24, 2012
  • Initiation of Service: August 31, 2012